Concrete Volume Calculator

Engineering Calculators › Concrete Volume Calculator
Engineering · Civil

Concrete Volume Calculator

How much concrete you actually need — cubic yards, bags and cost — for slabs, footings, round columns, walls and stairs, with waste allowance and a rebar estimate.

Concrete needed

How Much Concrete Do You Need?

The real question is never just volume — it is how many bags, how many cubic yards, and what it costs. This calculator takes the dimensions of a slab, footing, round column, wall or set of stairs and answers all three at once, with a waste allowance built in and an optional rebar estimate.

The Shapes and Their Formulas

ShapeVolume
Slab / footinglength × width × thickness
Round column / pierπ × radius² × height
Walllength × height × thickness
Stairswidth × run × rise × n(n+1)/2

Everything is converted internally and reported in cubic yards, cubic feet and cubic meters so the number fits whatever you are ordering.

Bags or Ready-Mix?

Small jobs get bagged; big pours get a truck. As a rule of thumb a cubic yard is 27 cubic feet, so it takes about 45 of the 80 lb bags (0.6 cu ft each) to make one cubic yard — which is why anything past roughly half a yard is usually cheaper and easier as ready-mix.

Bag sizeYieldBags per cu yd
80 lb0.60 cu ft45
60 lb0.45 cu ft60
40 lb0.30 cu ft90

Always Order a Little Extra

Subgrade is never perfectly flat and some concrete is always lost to spillage and over-excavation, so a 5 to 10 percent waste allowance is standard — the calculator adds it for you. Running short mid-pour and waiting on a second batch creates a cold joint, which is far worse than buying one extra bag.

Frequently Asked Questions

How many 80 lb bags are in a cubic yard?

About 45, since a cubic yard is 27 cubic feet and each 80 lb bag yields roughly 0.6 cubic feet.

How thick should a slab be?

Four inches is typical for patios and walkways; five to six inches for driveways and anything carrying vehicles. Thickness drives the volume directly.

Does the rebar estimate include laps?

No — it is a simple grid total (bars each way at your spacing). Add roughly 10 to 15 percent for laps, bends and waste when ordering.

Estimates are for planning only. Actual quantities vary with formwork, subgrade, spillage and over-excavation. Confirm structural concrete dimensions, mix and reinforcement against the project drawings and the applicable building code.
Scroll to Top

The calculators and tools on Formula Factory are provided for general guidance and informational purposes only. Results are estimates based on standard formulas and the values you enter — they do not constitute professional engineering, electrical, or architectural advice. Always verify calculations with a qualified professional before making decisions for any safety-critical, code-compliance, or commercial application. Formula Factory makes no representations or warranties as to the accuracy or completeness of any result, and accepts no liability for errors, omissions, or any outcomes arising from reliance on this information.